Briefings start for £1bn Midland Mainline Electrification plan

The electrification programme is a continuation of the completed London to Corby electrification.

Part of the electrification programme has already been procured with contractor SPL delivering electrification between Kettering and South Wigston.

Rail infrastructure chiefs will set out the latest thinking for the project.

Also Network Rail will be canvassing for ideas on the most efficient delivery method to avoid cost overruns that dogged previous electrification projects.

The next stage of procurement for the Midland Main Line Electrification programme is split into seven routes and includes over 67 structures.

• Route Section 2 (RS2) – Wigston South to Syston 19.5km

• Route Section 3 (RS3) – Syston to Trent Junction 28.7km

• Route Section 4 (RS4) – Sheet Stores Junction to Chaddesden Sidings (Derby) 15.7km

• Route Section 5 (RS5) – Trent Junction to Nottingham 13.1km

• Route Section 6 (RS6) – Chaddesden Sidings (Derby) to Toadmoor Tunnel 16.7km

• Route Section 7 (RS7) – Toadmoor Tunnel to London Road 43.3km

• Route Section 8 (RS8) – London Road to Sheffield North 2.5km

Network Rail holding a Midland Main Line electrification market engagement briefing event at Pride Park Stadium, Derby and online as an MS Teams live event on 15th June 2022 at 10:00 and 13:00.

Firms can register an interest via the below Eventbrite link by the 10th June, 5pm.

 